Revised benchmark CAPEX will help the VGF bidding process under the NSM Phase 2


20 November 2012 | Jasmeet Khurana

Revised benchmark CAPEX will help the VGF bidding process under the NSM Phase 2

Jasmeet Khurana, Market Intelligence Consultant at BRIDGE TO INDIA has expertise in project performance benchmarking, success factors for module sales, financing and bankability of projects in India.

The Central Electricity Regulatory Commission (CERC) recently announced the revised benchmark capital cost for solar projects. In the order, dated October 25th 2012, the benchmark capital expenditure (CAPEX) for solar photovoltaic (PV) projects in India has been reduced to INR 8cr/MW. This is largely driven by the falling costs of PV modules. This has resulted in a 20% reduction from the earlier benchmark of INR 10cr/MW. As per our analysis, this revision of the benchmark CAPEX by the CERC ahead of the announcement of guidelines for phase two of the National Solar Mission (NSM), will pave the way for setting up of more reasonable allocation and execution procedures for projects under the policy.

  • New allocation of projects under phase 2 of the NSM will be based on bidding for Viability Gap Funding (VGF)
  • The maximum VGF that can be provided is based on a percentage of the benchmark CAPEX
  • A more realistic estimate of the benchmark CAPEX benefits the bidders by correctly estimating the required guarantee to be paid
  • As per our analysis, the revised benchmark CAPEX is a more realistic estimate of actual market costs

It is proposed that new allocations under the phase two of the NSM will use bidding based on Viability Gap Funding (VGF) as a mechanism to allocate new projects (to read more, download the October 2012 edition of the India Solar Compass). Under the VGF mechanism, the project developer that requires the minimum fund from the government to make their project viable will be allocated the project.

The maximum VGF that can be provided to any developer will be based on a fixed percentage of the benchmark capital cost. This percentage will be fixed by the Solar Energy Corporation of India (SECI). To draw out the guidelines for this mechanism, the SECI needs to set the limit of the funding it can provide to the projects in order to budget for the fund requirements for the upcoming bidding process. For example, if the VGF can be provided for up to 25% of the benchmark cost of INR 8cr/MW, SECI may need to provide a maximum VGF of INR 2cr/MW.

The mechanism will be designed in such a way that the developer asking for the minimum fund will be required to submit the maximum bank guarantees. This is done to ensure project completion. If the benchmark costs, as determined by CERC, do not reflect the actual costs, developers can be expected to pay unrealistic performance and other guarantees. A benchmark capital cost that reflects the actual market costs will only help in making the guarantees more reasonable. As per our analysis, this revision of the benchmark CAPEX by the CERC ahead of the announcement of guidelines for phase two of the NSM, will pave the way for setting up of more reasonable allocation and execution procedures for projects under the NSM.

For a complete background on the National Solar Mission, read our latest publication, the INDIA SOLAR HANDBOOK.

Read why the revised benchmark CAPEX might not be good news for REC project developers in India.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top