Solar tenders like Indian rail — you can almost bet on delays


05 October 2015 | BRIDGE TO INDIA

Solar tenders like Indian rail — you can almost bet on delays

The recent National Solar Mission (NSM) tenders have been delayed multiple times before and are again delayed now. This pattern of delays is not new.

  • Only one of the 30 odd bids in India has gone through without significant extensions or delays
  • Main culprits are process delays by implementation agencies and requests for time extension from developers – these delays affect sector development as many players, particularly the new entrants are not conditioned to respond to the way business is carried out in India
  • MNRE should play a key role in streamlining the somewhat disorganized tender process so as to improve the ‘ease of doing business’

Out of the approximately 30 solar tenders so far in India, only one has been submitted on the original date mentioned in the bid document – this was the 500 MW tender in Karnataka in June 2014. Other than this, most bids have been delayed by a few months. A bid for a 50 MW tender in Haryana was delayed by as much as five months.

Another cause for concern for the new NSM tenders is the decreasing accessibility under the online tendering process. Earlier, all new tenders were announced in the newspapers, on Ministry of New and Renewable Energy’s (MNRE) website and on the website of the tendering authority like NTPC Vidyut Vyapar Nigam Limited (NVVN) or Solar Energy Corporation of India (SECI). The openly available tenders allowed the media and the market to scrutinize and publicize them for the global audience. Under the new NSM bids released by National Thermal Power Corporation (NTPC), the announcements and the bid documents are only available on a paid portal. This paid portal and its somewhat complicated access procedures are an unnecessary hassle for developers.

With the floodgates on solar capacity allocations now open in India, there is an urgent need to streamline processes. By improving their internal planning and providing advance notice of (more realistic) bidding timelines, the tendering authorities can provide better transparency to the market and minimize delays. MNRE should also focus on improving the ‘ease of doing business’ by for example, developing a special online portal for launching all central and state solar project tenders in one place and possibly, spreading the tenders evenly over time.

We expect such measures to boost confidence in the sector and improve participation particularly from the international developers.


Recent reports

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

Inter-state OA — opportunities and challenges

Inter-state OA — opportunities and challenges

Inter-state transmission system (ISTS) open access (OA) renewable market is growing strongly on the back of multiple drivers including a waiver from ISTS charges together with decarbonisation pressure on corporates and streamlined transmission connectivity approval process. However, the ISTS route savings are viable only for projects commissioned by June 2026 (at least 75% ISTS charge waiver).

India Corporate Renewable Brief | Q3 2023

India Corporate Renewable Brief | Q3 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

To top