Subdued bid interest for SECI’s 500 MW tender in Maharashtra


18 January 2016 | BRIDGE TO INDIA

Subdued bid interest for SECI’s 500 MW tender in Maharashtra

Earlier this month, bids were submitted to Solar Energy Corporation of India (SECI) for 500 MW of solar PV projects in Maharashtra under Viability Gap Funding (VGF) mechanism. Out of the total capacity under this tender, 50 MW of projects are reserved for modules meeting domestic content requirement (DCR). Key highlights of this tender are – minimum project size of 10 MW, no maximum limit, land to be procured by developers, fixed tariff of INR 4.43/kWh and VGF of up to INR 10 million/MW (INR 13.1 million/MW for DCR category) payable in 6 instalments (50% on project COD, followed by 5 annual instalments of 10% each). Bidders will be allocated projects on the basis of most competitive VGF quotes.

The tender has received bids from 14 developers for total capacity of less than 1.8 GW in contrast to NTPC’s recent 500 MW tender in Andhra Pradesh which received bids aggregating 5.5 GW from 30 bidders.

  • MNRE reduced the fixed tariff drastically from INR 5.43/kWh (plus an annual escalation of INR 0.05/kWh for 20 years) in earlier VGF rounds taking note of recent bids of INR 4.63/kWh in Andhra Pradesh just 10 days before bid submission;
  • Bid response is highly subdued as compared to recent allocations by NTPC and some states;
  • We expect similar muted response for SECI’s three upcoming tenders in Uttar Pradesh, Gujarat and Andhra Pradesh.

Figure 1: Bid response in recently concluded tenders

We believe that the SECI tender has two key differences in comparison to other recent tenders, which are likely to result in higher tariff (or VGF) expectations for developers. As these projects will be implemented outside government solar parks, land acquisition will be a challenge for developers particularly for large project sizes. As contiguous land is unlikely to be available in large sizes, developers will not benefit from economies of scale. Secondly, the market’s higher risk perception of SECI as an off-taker in comparison to NTPC is also likely to have an upward impact on the bids. Finally, we believe that the recent hardening of module prices and INR depreciation against the USD may also have a similar upward impact on the bids.

SECI has issued 3 other tenders for projects in Gujarat (250 MW), Uttar Pradesh (440 MW) and Andhra Pradesh (500 MW) respectively under VGF route. Bids are expected to be received for these tenders over the next two months. We expect similar muted response for all three tenders for various reasons including smaller project sizes, low radiation (Uttar Pradesh), high solar park charges (Gujarat).


Recent reports

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

Inter-state OA — opportunities and challenges

Inter-state OA — opportunities and challenges

Inter-state transmission system (ISTS) open access (OA) renewable market is growing strongly on the back of multiple drivers including a waiver from ISTS charges together with decarbonisation pressure on corporates and streamlined transmission connectivity approval process. However, the ISTS route savings are viable only for projects commissioned by June 2026 (at least 75% ISTS charge waiver).

India Corporate Renewable Brief | Q3 2023

India Corporate Renewable Brief | Q3 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

To top