Weekly Update: Uttar Pradesh releases RfP for 300 MW


05 August 2014 | Akhilesh Magal

Weekly Update: Uttar Pradesh releases RfP for 300 MW

The state of Uttar Pradesh released a Request for Proposal (RfP) for 300 MW of solar PV last week (click here to access). This is a part of Uttar Pradesh’s solar policy announced last year that targets 500 MW by 2017. In March 2013, the state had announced an RfP for 200 MW out of which 110 MW have already been signed. The highlights of this RfP are:

  • The Power Purchase Agreement (PPA) term is the shortest so far in the country at 12 years. Although there is a possibility to extend the PPA tenure, it would only be at the Average Pooled Purchase Cost (APPC) which is currently at INR 2.77 /kWh
  • Each developer can bid for capacities between 5 MW and 100 MW in multiples of 5 MW. Last date for submitting bids is September 8th 2014.
  • Uttar Pradesh Power Cooperation Ltd. (UPPCL), the state nodal agency will sign the PPA and shall also be responsible for constructing all evacuation infrastructure

The story so far

Uttar Pradesh announced its solar policy in 2013 and aims to achieve 500 MW of solar by 2017. This is the second RfP that has been announced so far, the first being a 200 MW RfP that was released in March 2013. Out of the 200 MW auctioned, PPAs worth 110 MW have already been signed. With the recent announcement of 300 MW, it appears that the state could achieve its policy target much earlier than anticipated. Therefore, Uttar Pradesh could potentially expand its target like some other states such as Karnataka.

There were six successful developers under the first RfP of 200 MW (Essel Infra, Moser Baer, Sree Developers, Azure, Reflex, Jackson and DK Infracon). The tariffs were among the highest in the country (INR 8.01 to INR 9.33/kWh). The high tariffs were likely a result of the shorter 12-year PPA. Some developers have commented that a short PPA could actually be an advantage, because this gives them flexibility to re-negotiate contracts after year 12. However, the policy clearly states that PPA price after year 12 will be at the APPC prevailing at that time. The current APPC in Uttar Pradesh is at INR 2.77/kWh. Assuming a reasonable escalation of around 3%, this gives us a tariff of INR 3.95/kWh in year 13. We therefore see no reason, how a shorter PPA could be advantageous to any developer. Moreover, it drives up the solar price for the state and ultimately for the end consumer.

BRIDGE TO INDIA expects the bids to be in a range of INR 7.8/kWh to INR 8.6/kWh this time around.

Bidding pre-requisites

Bidders are required to have had previous experience in setting up infrastructure projects. Bidders are required to show for projects worth INR 2.5 cr (USD 400,000) for every MW that they apply for.The selection process will be through a reverse bidding process – the standard process for most solar projects in India today. However, the L1 (lowest bid by any bidder) shall not be enforced on all developers (unlike Andhra Pradesh and Tamil Nadu). Bidders shall be given 13 months to commission projects of capacities lower than 25 MW and 18 months for higher capacities, which is more than adequate.

PPA terms and risks

The PPA signatory would be Uttar Pradesh Power Cooperation Ltd. (UPPCL). The company is already in poor financial health. In FY 2013-14, the company reported a net loss of over 7,000 cr (USD 1.16 bn). In fact, the Ministry of Power with ICRA and CARE released a report that rates distribution utilities across the country on financial health. UPPCL secured the second lowest rating (click here to access that report). Last year saw prominent power producers like Reliance Power and Lanco infratech sever PPA with UPPCL due to non-payment of dues (see article). The Central Government through the Power Financing Corporation (PFC) had to step in and back up UPPCL (see article). These instances show that the PPAs with UPPCL are risky and developers need to factor in adequate risk into their business models.

Akhilesh Magal is a Consultant at BRIDGE TO INDIA.


Recent reports

Corporate renewable market -alternative procurement options

Corporate renewable market -alternative procurement options

Corporate consumers seeking to increase share of renewable power in their consumption mix have the option of using multiple short-term procurement routes like green power exchange, renewable energy certificates (RECs), I-RECs and green tariffs.

India Solar Rooftop Map | December 2023

India Solar Rooftop Map | December 2023

India Solar Rooftop Map is an info-graphic report providing a snapshot of rooftop solar market in India – capacity addition across states and consumer segments, market share of leading players and other key trends. Total rooftop solar capacity is estimated to have reached 14,484 MW by end of 2023. Total new installations in 2023 are estimated at 2,856 MW, up only 8% over previous year.

India Solar Map | December 2023

India Solar Map | December 2023

India Solar Map 2023 is an info-graphic report covering growth of utility scale solar sector – national and state-wise commissioned and pipeline capacity, leading market players and portfolio details of top 16 project developers. Capacity addition in 2023 fell 51% YOY to 5,924 MW taking total utility scale solar capacity to 59,840 MW. Total project pipeline stands at a record 74,161 MW.

India Corporate Renewable Brief | Q4 2023

India Corporate Renewable Brief | Q4 2023

This report provides an update on key trends and developments in the corporate renewable market including capacity addition, key players, policy & regulatory issuance, financing, PPA tariffs and other market trends.

India PV Module Intelligence Brief | Q4 2023

India PV Module Intelligence Brief | Q4 2023

This report captures quarterly trends in module demand and supply, import and domestic production volumes, supplier market shares, break-up by technology and rating, global market scenario, pricing trends across the value chain, key policy developments and market outlook.

India Solar Compass | Q4 2023

India Solar Compass | Q4 2023

This report provides a detailed update of all key sector developments and trends in the quarter – capacity addition, leading players, tenders and policy announcements, equipment prices, financial deals and other market developments. It also provides market outlook for the next two quarters.

To top